Welcome to the
Village of Altamont
115 Main Street P.O. Box 643
Altamont, New York, 12009

Phone: (518) 861-8554 Fax: (518) 861-5379



 

Comprehensive Planning Report September 2006

Village of Altamont

Comprehensive Planning Committee

Synopsis of August and Early September 2006 Progress

  • The Committee continued to refine goals and strategies and the draft Plan through the month of August. This process is intended to be a methodical and, as you can imagine, is therefore proving to be a lengthy process. For example, we are now meeting weekly to move this along as expeditiously as possible .
  • As reference, we have outlined the following required steps toward completion and implementation of the Comprehensive Plan:
  • Complete the full draft Plan and present to the Village Board and public for comment (Estimate to complete: September/October 2006)
  • Submit a revised Plan, based on this input, to the Village Board for their adoption (Estimate to complete: November 2006). Adoption steps also includes:
  • Submittal to Albany County Planning Board for their review, comment and approval as per State Law 239-m
  • State Environmental Quality Review (SEQR) process
  • Public Hearing
  • Official Adoption of Plan via Village Board Resolution
  • Amendment of Sub-Division and Zoning regulations in accordance with the recommendations of the adopted Plan (Estimate to complete:

          December 2006 to March 2007). This includes:

                            Draft Language that is consistent with the direction of the Plan

                            Adopt amendments and or new regulations as per Village law

 

                            Work plans for utilities and budgeting for long-term goals       

                            identified

Therefore, as noted on the agenda for this evening, given the timeline necessary to accomplish all that is required within a Comprehensive Plan and other factors, the Committee is proposing a six-month extension of the sub-division moratorium currently in place through the month of September to allow proper completion of the plan. A Public Hearing is scheduled for 8:00 pm to review this topic. I will outline farther the justifications in a statement just prior.

Dean Whalen, Village Trustee, Committee Chair September 4, 2006